25 January 2023- Weather permitting, on Thursday, January 26th, work crews from the City’s Department of Public Works will be replacing the traffic signal controller cabinet at the intersection of N. Burhans Blvd. and Park Lane. In order the complete the work, the traffic signal must temporarily be taken out of service, and the following street closures will be implemented:

Park Lane: closed between N. Burhans Blvd. and Pennsylvania Avenue

N. Burhans Blvd.: left turn lanes at the intersection will be closed

The work is scheduled to begin at 9:00 AM, and is expected to be completed by 2:00 PM.

Emergency vehicles will be able to pass through the intersection on N. Burhans Blvd., but will not be able to pass through this section of Park Lane while the closure is in effect.

Please contact the City’s Department of Public Works at 301-739-8577, ext. 177 if you have any questions regarding this advisory.


Weather permitting, on Thursday, January 26th, work crews will be excavating test pits at the intersection of Frederick Street and Eastern Blvd. to locate underground utilities. This work is related to the reconstruction of the traffic signal at that intersection.

In order to provide space for excavation equipment, temporary lane shifts and lane closures will be required on both streets at the intersection. Flagmen will be used to direct traffic around the work zone.

The work is scheduled to begin at 9:00 AM, and should be completed by 2:30 PM. Motorists may encounter temporary traffic delays, but will be able to pass through the work area.

Emergency vehicles will be able to pass through this intersection while the work is being performed.